Issues are presented concerning the implications of the judgement made in the case of Discain Project Services Ltd vs. Opecprime Development Ltd concerning adjudication enforcement. The adjudication provisions of the Construction Act are discussed.

author: Bingham, Tony
Discain Project Services Ltd, Opecprime Development Ltd

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA

Looking for trouble

Article Abstract:

Problems arising from attempts to bring non-dispute issues to adjudication are considered. Some adjudicators fail to recognize that they do not have the power to adjudicate on issues that are only claims, not proper disputes.

author: Bingham, Tony

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA

Get back on the field, ref

Article Abstract:

A legal case between Bowmer and Kirkland (London) and Bloor Construction (UK) has resulted in a ruling that adjudicator's are able to correct their own errors, provided this occurs within an acceptable time period.

author: Bingham, Tony
Judicial review of administrative acts, Bloor Construction (UK) Ltd, Bowmer and Kirkland Ltd.

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


subjects list: Cases, Laws, regulations and rules, Column, Administrative procedure, Construction industry
This website is not affiliated with document authors or copyright owners. This page is provided for informational purposes only. Unintentional errors are possible.