Article Abstract:
Heuristic algorithms were developed to address scheduling problems with multiple modes and dedicated resources resulting from production and project management. The algorithms, which were derived from a mode graph, are based on the iterative solution of subproblems. They involve determination of a viable assignment function and resolution of a sequencing problem through the use of a subgraph-derived sequencing procedure.
User Contributions:
Comment about this article or add new information about this topic:
Article Abstract:
A new study uses the learning curve introduced by Biskup (1999) to investigate a number of scheduling problems with learning considerations.
User Contributions:
Comment about this article or add new information about this topic:
Article Abstract:
The solution of a short-term planning problem in a shop consisting of unrelated parallel machines in the glass bottle industry is described.
User Contributions:
Comment about this article or add new information about this topic: