A genetic algorithm for multi-mode resource constrained project scheduling problem

Article Abstract:

A genetic algorithm was developed for solving a class of nonpreemptive multi-mode resource-constrained project scheduling problem involving an activity that can be performed in duration or resource requirements. The genetic algorithm for multi-mode resource-constrained project scheduling problem incorporates the problem-specific knowledge of the application domain to form a non-standard representational scheme. The introduction of the expanded representation also required the definition of new domain-dependent crossover and mutation operators.

Author: Mori, Masao, Tseng, Ching Chih
Linear programming

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA


Multi-resource shop scheduling with resource flexibility

Article Abstract:

A shop scheduling problem is presented characterized by multi-resource processing, resource flexibility and non-linear routings. The problem involves operations that require multiple resources to be undertaken. It also takes into consideration an operation that may probably have more than one predecessor and/ or successor on the routing. A neighborhood structure that can be utilized to obtain a local search algorithm, such as tabu search, was created.

Author: Lasserre, J.B., Dauzere-Peres, S., Roux, W.
Analysis, Heuristic, Heuristics (Psychology)

User Contributions:

Comment about this article or add new information about this topic:

CAPTCHA



Subjects list: Research, Scheduling (Management), Production control